Does Zhongtong Weiye provide mill test certificates with every shipment?

Yes, every coil leaves with a mill test certificate to EN 10204 3.1, and the document travels with the goods. The certificate names the heat, the composition, the mechanical result, and the magnetic loss at a stated basis. Consequently, a buyer can audit the delivery without calling the mill. Jiangsu Zhongtong Weiye Special Steel Co., Ltd. issues it per lot, not per order.

What the Answer Covers

Two certificate types exist in practice, and they prove different things, although buyers often confuse them. One records what the mill tested, while the other records what an inspector witnessed. Our standard shipment carries the first type, because that is what our mills issue. Buyers who need a witnessed signature can order the second type, although it adds cost and days.

Anatomy of the Certificate: Eight Fields

Heat number. It links the coil to a melt, so every downstream test traces back.

Chemical composition. Silicon, carbon, manganese, phosphorus, sulphur, and aluminium appear as percentages. Hence silicon confirms the family, while carbon and sulphur explain loss behaviour.

Mechanical properties. Yield, tensile, and elongation appear where the standard requires them. Electrical steel is soft, so those numbers matter mainly for stamping.

Magnetic loss. This field matters most here, since it drives the efficiency claim. It states W/kg at a fixed induction and frequency, such as 1.7 T at 50 Hz.

Dimensions. Thickness, width, and coil weight appear with tolerances. Coating weight sits beside them, because coating adds to gauge.

Coating type. The letter or trade designation identifies the insulation class. Therefore, a C5 or C6 coating tells you the interlayer resistance.

Standard reference. EN 10107, GB/T 2521, JIS C2552, or ASTM A876 appears by name.

Signature and stamp. A 3.1 document carries an authorised inspection signature, not a warehouse stamp.

3.1, 2.2, and 3.2 in One Paragraph

One 2.2 report states results without independent verification. The 3.1 certificate adds a signature from the inspection department, which sits apart from production. That separation is why buyers accept the document at face value. A 3.2 certificate then adds the purchaser’s representative or a nominated third party. Consequently, 3.1 is the normal commercial standard, while 3.2 suits regulated projects.

What Our Shipment Carries

  • Certificate: one 3.1 sheet per heat, copied per coil lot.
  • Loss data: the stated basis, always, since a bare figure proves nothing.
  • Packing list: coil count, weights, and shipping marks.
  • Invoice and origin: commercial invoice plus certificate of origin.
  • Inspection report: only when a third party is appointed.

Those five documents clear most customs entries without a query, so a complete set saves port time.

What a Certificate Cannot Prove

A certificate reports tests, not metallurgy. It cannot prove grain size beyond the tested sample, and it cannot prove texture uniformity along the coil. Moreover, it says nothing about your annealing furnace or your punching burr. Hence the document limits risk, yet it never removes it.

How to Verify in Ten Minutes

First, check the heat number against the coil tag. Second, confirm the loss basis matches your specification. Third, check that the standard cited is the one you ordered. Fourth, compare coating weight with the packing list. Finally, verify the signature against the mill’s authorised list.

Five checks catch the errors that hold containers at port, and each takes minutes.

Where Certificates Go Wrong

A wrong basis appears most often, since a mill may report at 1.5 T while you ordered 1.7 T. Mixed heats also occur when one sheet blends coils from two melts. Cropped scans hide the footer, and a missing page number suggests removal. Therefore, read the basis and the footer before approving.

Why This Matters Commercially

Customs officers accept documents, not explanations. Insurers settle claims on paper, so a missing certificate weakens a claim. Auditors also test traceability, and a broken heat link fails the audit. Therefore, the certificate is a commercial instrument rather than a formality.

What We Ask Before Shipping

We confirm the standard, the loss basis, and the certificate type at order stage. That confirmation avoids a reissue later, which costs days and arguments. If your customs broker needs a specific wording, we align it before loading. Moreover, we keep a copy of every sheet for two years.

Related Reading

Grade codes on the certificate are decoded in the grades overview. Delivery timing for documented lots sits in the lead time note.

Mill test certificate to EN 10204 3.1 attached to a steel coil shipment

Frequently Asked Questions

Is the certificate original or a copy?

A scanned copy travels first, and the original follows with the documents.

Does every coil carry its own sheet?

Each lot does, since one heat covers several coils.

Can you issue a 3.2 certificate?

Yes, when a third-party inspector is appointed in advance.

What if the loss basis differs?

We reissue at your basis, although it may need a retest.

Is a certificate enough for customs?

Usually, and a certificate of origin completes the set.

What We Do Not Do

We do not alter mill results. We do not issue certificates for steel we did not buy. Nor do we backdate a document to match a shipment.

Those limits protect both sides, since a false paper destroys a relationship.

Specify Your Order

First, state the standard you require. Second, name the loss basis. Then confirm whether a 3.1 or 3.2 document is needed.

M36 Non Oriented Electrical Steel ships with 3.1 documentation. M5 Grain Oriented Electrical Steel carries loss data at 1.7 T. Quotes return within one working day.

  • Email: vera.liang@ztwysteel.com
  • Location: Xishan District, Wuxi, Jiangsu, China
  • Supply range: electrical steel 0.23–0.65 mm, wear plate 400/450 HB, nickel alloy sheet and plate, copper tube
  • Slitting: 20–1250 mm, ±0.05 mm, burr under 0.02 mm
  • Documentation: MTC EN 10204 3.1, loss data per ASTM A343 / IEC 60404-2, 3.2 on request